· end 2026-09-155d left
Open
14 of 19 cards · 4 stages
5
Working✓ 0/1Urgent07/10
Ship 34 heat-shield tile bonding
May 1 → Jul 10💬 2JQ
WorkingUrgent46d late
Booster 16 Raptor 3 engine install (33 units)
Jun 1 → Jul 25💬 1S
Pending Review06/25
Hot-stage ring refurbishment
May 15 → Jun 25T
5
WorkingHigh06/30
Booster 16 cryo proof + structural load test
Jun 10 → Jun 30D
OverdueHigh06/12
Pad A deluge system flow verification
May 25 → Jun 12💬 1T
OpenUrgent49d late
Ship 34 six-engine static fire
Jul 15 → Jul 22DS
OpenUrgent32d late
Booster 16 33-engine static fire
Aug 1 → Aug 8D
5
WorkingHigh41d late
FAA launch licence modification package
Apr 1 → Jul 30B
OpenUrgent20d late
Flight termination system install + arm test
Aug 10 → Aug 20C
Open12d late
Payload mass simulator integration
Aug 15 → Aug 28R
OpenUrgent4d late
IFT-7 Flight Readiness Review
Sep 1 → Sep 5💬 1AB