  • IFT-7 weekly integration standup

    2026-06-18 · 00:00 · 5 attendees

    Decisions

    Hold IFT-7 target at 2026-09-15 — no slip declared this week. Second torque crew approved for Booster 16 engine install.

    Action items

    Quinn: disbond rework burn-down chart by Friday Taylor: escalate the manifold valve with the supplier Sam: publish the revised engine-install curve

    Notes

    Tile bonding at 71%. The S29 disbond patch is the pacing item — 240 tiles to strip and re-bond. Raptor install running 2 units/day against a plan of 3; Sam is adding a second torque crew. Deluge verification still blocked on the replacement manifold valve, ETA 2026-06-24.

  • NASA TIM — Starship HLS commonality

    2026-06-11 · 00:00 · 3 attendees

    Decisions

    V2 substrate declared common; attachment hardware stays variant-specific.

    Action items

    Alex: send the V2 arc-jet series A data pack to MSFC Avery: propose three propellant-transfer demo windows

    Notes

    NASA asked whether the V2 tile stack flies on the HLS demo article. Alex confirmed the substrate is common but the attachment differs. Propellant transfer demo remains notional pending IFT-7 outcome.

  • IFT-6 catch anomaly review board

    2026-05-28 · 00:00 · 4 attendees

    Decisions

    Add a redundant proximity sensor on every strongback lock before IFT-7.

    Action items

    Casey: sensor redundancy design by 2026-06-30 Taylor: retrofit plan for both towers

    Notes

    Sensor B7 reported locked while the mechanism was still in transit, which triggered the first catch abort. Second attempt succeeded after a manual sensor override.