Meetings
3 meetings logged
IFT-7 weekly integration standup
2026-06-18 · 00:00 · 5 attendees
DecisionsHold IFT-7 target at 2026-09-15 — no slip declared this week. Second torque crew approved for Booster 16 engine install.
Action itemsQuinn: disbond rework burn-down chart by Friday Taylor: escalate the manifold valve with the supplier Sam: publish the revised engine-install curve
NotesTile bonding at 71%. The S29 disbond patch is the pacing item — 240 tiles to strip and re-bond. Raptor install running 2 units/day against a plan of 3; Sam is adding a second torque crew. Deluge verification still blocked on the replacement manifold valve, ETA 2026-06-24.
NASA TIM — Starship HLS commonality
2026-06-11 · 00:00 · 3 attendees
DecisionsV2 substrate declared common; attachment hardware stays variant-specific.
Action itemsAlex: send the V2 arc-jet series A data pack to MSFC Avery: propose three propellant-transfer demo windows
NotesNASA asked whether the V2 tile stack flies on the HLS demo article. Alex confirmed the substrate is common but the attachment differs. Propellant transfer demo remains notional pending IFT-7 outcome.
IFT-6 catch anomaly review board
2026-05-28 · 00:00 · 4 attendees
DecisionsAdd a redundant proximity sensor on every strongback lock before IFT-7.
Action itemsCasey: sensor redundancy design by 2026-06-30 Taylor: retrofit plan for both towers
NotesSensor B7 reported locked while the mechanism was still in transit, which triggered the first catch abort. Second attempt succeeded after a manual sensor override.