· end 2026-09-1551d left
Open
Mark is waiting on you1 pending approval
- create_doctypeCreate a High-priority task on SPAX-0001 to re-certify RTV-560 adhesive lot 4471 before the next tile bonding run.In session MSESS-2026-00219
Mark intel
- Bottleneck2026-06-18from: standup meeting
Strongback lock sensor B7 still gives false 'locked' during transit — Taylor has no spare sensor head, lead time from Honeywell is 6 weeks. Catch rehearsal on hold.
who: Taylor Singh
open transcript ↗ - Delayed2026-06-17from: standup meeting
IFT-7 static fire moved right by 9 days (2026-07-11 → 2026-07-20) — range availability, not hardware. Riley has notified NASA liaison.
who: Riley Okonkwo
open transcript ↗
Payment milestones
No milestones set.