Starship IFT-7 Preparation

SPAX-0001· NASA
· end 2026-09-1551d left
Open
ERPNext ↗Drive folder — none linkedChat space — none linked
Mark is waiting on you1 pending approval
  • create_doctype
    Create a High-priority task on SPAX-0001 to re-certify RTV-560 adhesive lot 4471 before the next tile bonding run.
    In session MSESS-2026-00219

Mark intel

  • Bottleneck2026-06-18
    from: standup meeting

    Strongback lock sensor B7 still gives false 'locked' during transit — Taylor has no spare sensor head, lead time from Honeywell is 6 weeks. Catch rehearsal on hold.

    who: Taylor Singh

    open transcript ↗
  • Delayed2026-06-17
    from: standup meeting

    IFT-7 static fire moved right by 9 days (2026-07-11 → 2026-07-20) — range availability, not hardware. Riley has notified NASA liaison.

    who: Riley Okonkwo

    open transcript ↗

Payment milestones

No milestones set.