- Re: S29 tile disbond rework — daily burn-down2026-06-19 15:42
240 tiles stripped, 84 re-bonded as of this morning. Holding the 2026-07-04 close date.
11 msgs· 3 attach· spacex.demovia avery.chen@spacex.demoOpen in Gmail ↗ - FAA licence modification — third RFI response2026-06-17 11:05
Attached is our response to RFI-03 covering the revised catch-abort corridor.
8 msgs· 5 attach· spacex.demo, faa.govvia blake.martinez@spacex.demoOpen in Gmail ↗ - Pad A deluge manifold valve — supplier escalation2026-06-16 08:20
Supplier now committing to 2026-06-24 ex-works. That still puts us 12 days late on verification.
14 msgs· 1 attach· spacex.demo, boschrexroth.comvia taylor.singh@spacex.demoOpen in Gmail ↗