Raptor 3 Engine Qualification

SPAX-0005
· end 2026-11-0198d left
Open
ERPNext ↗Drive folder — none linkedChat space — none linked

Meetings

2 meetings logged

  • Raptor 3 ORP vibration tiger team

    2026-06-19 · 00:00 · 4 attendees

    Decisions

    Hold SN-47 throttle-sweep sign-off until the CFD result lands.

    Action items

    Sage: CFD first-pass result by 2026-06-26 Drew: instrument SN-48 with two extra accelerometers

    Notes

    Signature reproduces only above 95% throttle and only after 180s of steady-state running. CFD re-run with the measured injector-face boundary is underway.

  • Raptor 3 qualification gate 2 review

    2026-05-14 · 00:00 · 3 attendees

    Decisions

    Gate 2 passed. Hot-fire matrix cleared to proceed.

    Action items

    Quinn: close the two minor actions by 2026-05-30

    Notes

    Turbopump and igniter qualification both closed clean. Gate 2 passed with two minor actions.