· end 2026-08-3011d late
Open
9 of 11 cards · 4 stages
4
WorkingUrgent07/05
ECLSS CO₂ scrubber throughput fix
May 12 → Jul 5💬 1C
Pending ReviewHigh06/24
Docking adapter soft-capture ring rebuild
May 20 → Jun 24C
3
Working07/10
Crew-11 seat liner fit checks (4 crew)
Apr 5 → Jul 10R
WorkingHigh53d late
Suit loop pressure-decay verification
May 25 → Jul 18C
OpenHigh28d late
Crew training — nominal + abort sim block
Jul 6 → Aug 12RS
2
OpenUrgent16d late
NASA Flight Readiness Review — Crew-11
Aug 17 → Aug 24💬 1B
Open43d late
LC-39A crew-access-arm certification
Jun 22 → Jul 28T
Columns are project stages. Click a card to edit. + on a column creates a card in that stage. Drag to move between stages. + Stage creates a new column.