Demo mode · SpaceX fixture data · no live backend
2
← Projects

Dragon Crew-11 Mission Prep

SPAX-0003· NASA
· end 2026-08-3035d left
Open
ERPNext ↗Drive folder — none linkedChat space — none linked

Meetings

2 meetings logged

  • Crew-11 mission readiness review #2

    2026-06-19 · 00:00 · 5 attendees

    Decisions

    ECLSS closure declared the single gating item for the Crew-11 FRR.

    Action items

    Casey: fan-curve retune results by 2026-06-26 Riley: confirm the sim block start date with the crew office

    Notes

    Scrubber throughput now at 96% of rated after the bed repack. NASA wants 100% before the FRR. Soft-capture ring rebuild is in review and expected to close this week.

  • NASA CCP technical interchange — ECLSS

    2026-05-22 · 00:00 · 3 attendees

    Decisions

    Full ECLSS acceptance re-run required before the FRR.

    Action items

    Casey: schedule the full acceptance re-run Riley: update the Crew-11 milestone chart

    Notes

    JSC accepted the bed-repack approach but asked for a full acceptance re-run rather than a delta test.