· end 2026-08-3035d left
Open
Meetings
2 meetings logged
Crew-11 mission readiness review #2
2026-06-19 · 00:00 · 5 attendees
DecisionsECLSS closure declared the single gating item for the Crew-11 FRR.
Action itemsCasey: fan-curve retune results by 2026-06-26 Riley: confirm the sim block start date with the crew office
NotesScrubber throughput now at 96% of rated after the bed repack. NASA wants 100% before the FRR. Soft-capture ring rebuild is in review and expected to close this week.
NASA CCP technical interchange — ECLSS
2026-05-22 · 00:00 · 3 attendees
DecisionsFull ECLSS acceptance re-run required before the FRR.
Action itemsCasey: schedule the full acceptance re-run Riley: update the Crew-11 milestone chart
NotesJSC accepted the bed-repack approach but asked for a full acceptance re-run rather than a delta test.