Heat Shield Tile System V2

SPAX-0006
· end 2026-10-1581d left
Open
ERPNext ↗Drive folder — none linkedChat space — none linked

Mark intel

  • Planned2026-06-18
    from: standup meeting

    Avery will run the V2 tile arc-jet campaign the week of 2026-06-29 — 24 coupons, two ablation profiles. Needs the Materion coating lot released by 06-26.

    who: Avery Chen

    open transcript ↗
  • Done2026-06-12
    from: standup meeting

    Tile V2 mechanical attachment redesign released to manufacturing — pin-and-clip replaces the bonded stud on 62% of the windward field.

    who: Alex Reeves

    open transcript ↗