Starlink Gen 2 Satellite Manufacturing
SPAX-0004· end 2027-03-01218d left
Open
Meetings
2 meetings logged
Starlink Gen 2 production rate review
2026-06-17 · 00:00 · 4 attendees
DecisionsLamination cell acceptance moved to 2026-08-20 to protect the rework burn-down.
Action itemsQuinn: daily rework burn-down posting Morgan: second thruster vendor qualification gate date
NotesCombined line output at 6.2/day against a 9/day target. Harness rework backlog down to 31 units from 96 but still past its due date.
Supplier design review — krypton thruster #2
2026-06-04 · 00:00 · 3 attendees
Decisions9-week qualification accepted with our test data supplied under NDA.
Action itemsMorgan: issue the qualification purchase order Casey: package the life-test dataset
NotesSupplier proposed a 12-week qualification. Casey pushed for a 9-week plan using our existing life-test data.