Starlink Gen 2 Satellite Manufacturing

SPAX-0004
· end 2027-03-01218d left
Open
ERPNext ↗Drive folder — none linkedChat space — none linked

Meetings

2 meetings logged

  • Starlink Gen 2 production rate review

    2026-06-17 · 00:00 · 4 attendees

    Decisions

    Lamination cell acceptance moved to 2026-08-20 to protect the rework burn-down.

    Action items

    Quinn: daily rework burn-down posting Morgan: second thruster vendor qualification gate date

    Notes

    Combined line output at 6.2/day against a 9/day target. Harness rework backlog down to 31 units from 96 but still past its due date.

  • Supplier design review — krypton thruster #2

    2026-06-04 · 00:00 · 3 attendees

    Decisions

    9-week qualification accepted with our test data supplied under NDA.

    Action items

    Morgan: issue the qualification purchase order Casey: package the life-test dataset

    Notes

    Supplier proposed a 12-week qualification. Casey pushed for a 9-week plan using our existing life-test data.